Modeling a process which can produce 2 different items with

Use this forum to post Vensim related questions.
Post Reply
Mattes_01
Member
Posts: 42
Joined: Mon Jul 05, 2010 6:05 am

Modeling a process which can produce 2 different items with

Post by Mattes_01 »

Hello @ all.

I got a question about modeling a process, which is able to produce 2 items.

Lets say I want to model an engine block casting production which is able to produce an usual steel engine block (1) and an magnesium engine block (2).

I want to model the production either just with a delay or with a delay and a queue (actually the production planner will only put as much material in the process as capacity is available, but as far as some production steps are processed cyclical or as a batch of 100 engines there will be still a queueing in the process).

The production of (1) has a certain delay distribution and the production of (2) has a different delay distribution (a longer production, because some steps take longer and other steps have to be done more often than for (1)).

There are 2 options to model this:
1. The first one is I calculate the overall/average delay (maybe depending on the input fraction) for all materials together and calculate the "input fraction" of (1) and (2). This fraction I will delay like the process and use it to split up the produced materials.
This option is quite inaccurate because it will not reflect the reality well, but it is simple.

2. I will split up the process in two paralell and equal processes with different delay times. Over here I have to see how I can handle capacity constraints and so on, but the result is more accurate, because all items of (2) will stay the correct time in the process.


My question now is, if someone is having some experience on the difference of both and on that issue.
Lets say you don't have 2 but 10 different materials, this will be a lot more work to do!

Maybe you have an idea, if you don't understadn what I am trying to say let me know and I will explaing better.
Thanks, Mattes_01
bob@vensim.com
Senior Member
Posts: 1107
Joined: Wed Mar 12, 2003 2:46 pm

Post by bob@vensim.com »

If the processes are the same (just with different process times) you can use a subscript for each process variation, then 2 and 10 are about the same complexity. If the structure of the process varies (some have queues, some don't and so on) this is messier. But if there are only 2 or 3 variations you can build each and subscript each then again 10 is the same as 3 in complexity.
Mattes_01
Member
Posts: 42
Joined: Mon Jul 05, 2010 6:05 am

Post by Mattes_01 »

Basically I think it is possible to only use different delay times, at least for the beginning.

Is there anything like a manual for these subscripts. In the modeling guide it isn't mentioned if I am not wrong.

Or just browse through the Vensim buildin manual/help?
I would like to see an example of the usage of subscripts to analyze it a bit to understand the mechanism behind.

Thank!
Administrator
Super Administrator
Posts: 4590
Joined: Wed Mar 05, 2003 3:10 am

Post by Administrator »

Chapter 17 in the user guide is the section on subscripts.
Post Reply